Fire Door Submittals: What to Include and How to Get Approved

Author: Esteban Galicia

Updated:

Fire-door submittal title card with ink sketches

A fire door submittal is the package of documents you send to the architect, the engineer or the building official to show that each rated opening uses a door, frame, glazing and hardware combination that is tested, labeled and listed for its rating. It usually holds a door schedule, product data, hardware information and listing proof. Requirements differ by jurisdiction, so the local plan review checklist always has the last word.

This guide explains what goes into the package, how to prove that an assembly matches its test, how review and approval work, and which mistakes slow a project down.

Ufdoors
Specify Fire-Rated Doors with Confidence
Ufdoors manufactures and installs fire-rated steel doors, frames, and hardware for projects focused on safety and NYC fire and safety standards.

TL;DR

  • A fire door submittal documents the door, frame, glazing, hardware and rating of every rated opening, so a reviewer can compare it with the plans and code.
  • The door schedule is the core document. It should show construction, rating, hardware type and closing method for each door.
  • Proof of a tested assembly rests on labels and third-party listings, not on the supplier’s description alone.
  • Local rules vary. Cities and fire departments publish their own checklists, and some ask for installer credentials and manufacturer cut sheets with listing numbers.
  • Approved documents must stay on site and be open to inspection, so keep the stamped set with the job.

Table of Contents

What a fire door submittal is

A submittal is a formal presentation of what you plan to install. The reviewer does not design the opening. The reviewer checks your proposal against the construction documents and the code. Under the model code, the building official examines the submitted documents to decide whether the described construction complies with the code and other pertinent laws or ordinances.

For fire doors, the question is simple. Does the opening protect the wall it sits in? A rated wall needs a rated opening. The rating of the door depends on the rating of the assembly it is installed in. NFPA guidance describes the steps this way:

  1. Find the required fire resistance rating of the wall or barrier.
  2. Use the tables in codes such as NFPA 101 to find the rating needed for the opening protection.
  3. Check that no footnote or modification in the code or table changes that rating.

The submittal then proves that your product choice meets the rating that came out of those steps.

When you need one

There are two common situations.

Permit plan review. Many fire departments and building departments ask for door information with the plans. One California fire authority requires that for new buildings, tenant improvements and additions, the door schedule lists door and frame construction, door rating, hardware type, panic hardware and closing method.

Replacement and repair permits. Some cities extend permit rules to replacements. Pompano Beach, Florida, requires a building permit to install, replace or make major repairs to commercial or residential doors and windows. Replacing a part that does not alter the approval or make the product unsafe is excepted. The submittal there includes a product approval and a plan showing location, size and type.

Doors with access control or delayed egress. Round Rock, Texas, asks for a plan submittal and permit when an egress door goes through a fire-rated wall, has electromagnetic locks or uses delayed egress. Free-egress doors that do not restrict exit are excepted. The package there includes a floor plan, project name and address, installer credentials and license details, and manufacturer cut sheets with UL listing numbers.

These three examples come from three different places. They show the pattern, not a universal rule. Before you assemble anything, find the checklist from the authority that has jurisdiction over your building.

In New York City, where we work every day, the local department and fire code add their own requirements. Confirm the current process with the city before you order.

When you need one

What goes in the package

The exact list comes from the project specification and the local authority. Most packages draw from the same set of documents.

The door schedule

The schedule lists every opening by number. For each one it should state:

  • Door and frame construction, such as hollow metal and gauge.
  • The fire rating of the door, for example 20, 45, 60 or 90 minutes.
  • Hardware type, including whether panic hardware is installed.
  • Whether the door is self-closing or automatic-closing.

Those are the items the fire authority cited above asks for. If your specification already carries the hardware information, include the specification as well.

Product data and cut sheets

Cut sheets show what the product is. They should carry the manufacturer name, model, size limits, rating and the listing number. Reviewers use them to tie each line in the schedule to a real, listed product.

Hardware listings

Hardware is part of the assembly. The Steel Door Institute states that proper hardware selections for fire doors can be verified through online listings published by UL LLC and Intertek. Those listings identify the hardware and other products that may be used in fire-rated assemblies. Hinges, closers, latches, exit devices and seals all belong in that check.

Our commercial door hardware guide explains how hinges, closers and locksets work together on a commercial opening.

Drawings and wiring diagrams

For electrified openings, such as magnetic locks or access control, reviewers often want wiring information and a floor plan. The Round Rock example above shows how specific this can get.

Installer information

Some jurisdictions ask for installer credentials and license details with the package. Add them when the checklist calls for them.

How to prove a door, frame and hardware match a tested assembly

This is where most review comments start. A fire rating belongs to a tested combination, not to a door alone.

UL Solutions explains that some fire doors ship as complete assemblies with frame, hardware and accessories. In other cases the door is supplied separately and assembled on site with the frame, glazing, hardware or other accessories. The protection level depends on the correct combination of these components.

Components that form a tested fire door assembly

Read the label

NFPA 80 requires fire doors, frames and windows to carry a label that shows the component was tested and listed by an organization the authority having jurisdiction accepts. The label includes:

  • The manufacturer’s name.
  • The marking of the third-party certification agency.
  • The component rating.
  • The fire test standard designation.
  • The temperature rise at 30 minutes, if it is less than 650°F (361°C).

This comes from NFPA’s fire door FAQ. The SDI adds that the mark of a labeling agency must appear on all labels applied to fire-rated doors and frames.

A reviewer will compare the label data to your cut sheet. If they do not match, the submittal comes back.

Know the test method

The SDI notes that the IBC recognizes two primary fire test methods for door ratings: ANSI/UL 10C and NFPA 252. Both are run under positive pressure. A specification may call out the test method or reference a section of a model building code. Cite the same method your specification uses.

Follow the installation instructions

UL Solutions states that fire doors are intended to be installed according to the manufacturer’s installation instructions. Attach or reference those instructions when the reviewer expects them.

Check the standard

NFPA 80 is the Standard for Fire Doors and Other Opening Protectives. It addresses installation, inspection and maintenance. Your local code adopts a specific edition, so use the one your jurisdiction names.

If you need to understand how ratings and sizes work before you assemble the package, read our guide to fire-rated doors, ratings and requirements. For large openings, see our page on oversized fire-rated doors, labels and limits.

How review and approval work

The process is usually the same, whatever the city.

  1. Submit. You send the package to the reviewer named by the project or the authority.
  2. Review. The reviewer checks the schedule, listings and plans against the code.
  3. Comments. If something is missing or does not match, the reviewer returns comments. You revise and resubmit.
  4. Approval. When the building official issues a permit, the construction documents are approved in writing or by stamp as “Reviewed for Code Compliance.”
  5. Retention. One reviewed set stays with the building official. The other goes back to the applicant, stays at the work site and is open to inspection.

That last point matters in the field. An inspector may ask for the approved set. Keep it on site, and keep it current when revisions are approved.

Deferred submittals

Some items are not fully designed when the main permit is issued. A deferred submittal lets specialist input come after permit issue, provided the architect of record lists those items as deferrals up front. Ask the design team whether your door package is a deferral on your project. Local rules decide whether that is allowed.

Common mistakes that slow approval

These errors follow from the requirements above. They are the ones we would check first.

  • An incomplete schedule. If the schedule leaves out the rating, hardware type, panic hardware or closing method, the reviewer has to ask for it.
  • A rating that does not match the wall. The opening rating comes from the assembly it sits in. Check the wall rating first, then the door.
  • Labels and cut sheets that disagree. The label shows the manufacturer, agency, rating and test standard. The paperwork must say the same thing.
  • Hardware that is not on a listing. Check each hardware item against the UL or Intertek listings.
  • Missing wiring or access control details. Electrified openings often need extra drawings.
  • Outdated forms. Jurisdictions revise checklists. Download the current one for each submission.
  • Mixing components without a tested basis. The door, frame, glazing and hardware must form a tested combination, as UL describes.
  • Lost approved sets. The stamped set needs to be on site and open to inspection.

Perspective

Most delayed submittals we see have the same cause. The paperwork was assembled after the product was chosen, and the two did not line up.

Our approach is to start with the opening. Confirm the rating, then pick the door, frame and hardware as one assembly, and write the schedule from that choice. The cut sheet, the label and the schedule then say the same thing.

We manufacture and supply fire-rated steel doors, hollow metal frames and commercial hardware, and we work to NYC fire and safety standards. Because we also install and maintain what we supply, we see where paperwork meets the actual opening. Contractors and property managers who bring us the schedule early save time at review and on site.

Speed matters too. Our same-day or next-day delivery is designed for jobs where a failed inspection or a damaged door cannot wait. Over 5,600 clients have worked with us on that basis.

Esteban

After approval: installation, inspection and records

Approval is not the end. NFPA 80 covers inspection and maintenance as well as installation. According to one Texas fire marshal’s FAQ, testing and inspection of fire doors are required on completion of installation, at least annually afterward and after any maintenance or alteration. The same office says a certified third-party contractor must perform the NFPA 80 and 105 testing. Your local authority sets its own rule, so confirm it.

Keep these records together:

  • The approved submittal set and stamped plans.
  • Cut sheets, listings and installation instructions.
  • Inspection reports and corrections.
  • Repair and maintenance records for each opening.

For New York projects, see our page on fire door inspection in NYC. If a door fails, our fire door repair service covers commercial openings. A commercial door maintenance program keeps the records and the work on a schedule. For new work, we describe our door and frame installation in NYC on a dedicated page.

A practical checklist before you submit

  1. Get the current checklist from the authority that reviews your project.
  2. Confirm the wall rating and the required opening rating.
  3. Build the door schedule with construction, rating, hardware type, panic hardware and closing method for every opening.
  4. Collect cut sheets with listing numbers for doors, frames, glazing and hardware.
  5. Check hardware against the UL and Intertek listings.
  6. Add wiring diagrams and floor plans for electrified or delayed egress openings.
  7. Add installer credentials if the checklist asks for them.
  8. Ask the design team whether any part is a deferred submittal.
  9. Submit, track comments and resubmit promptly.
  10. File the stamped set at the work site.

Order the right assembly the first time

A clean submittal starts with the right product. We supply fire-rated steel door units with matching hollow metal frames, plus commercial hardware, and we can install and service them. Pricing is quoted on request, and bulk order pricing is available for contractors and property managers.

28 x 80 Steel Door Slab, Single Cylindrical Prep – 20 Gauge, Fire-Rated - 90 Min

Browse the fire-rated steel doors collection or the full catalog of doors, frames and hardware. For a specific size or a rush job, start at ufdoors.com.

FAQ

What is the difference between a door schedule and a submittal?

The door schedule is one document inside the submittal. It lists each opening with its construction, rating, hardware and closing method. The submittal also includes product data, listings and any drawings the reviewer requests.

Do replacement doors need a submittal?

It depends on the city. Pompano Beach, for example, requires a permit for replacing commercial doors, except when only a part is replaced without changing the approval. Check with your local building or fire department before you order.

Who reviews a fire door submittal?

The building official reviews construction documents for code compliance, and a fire department may review the door information as well. Some projects route hardware and door packages through the architect first. Ask the design team who receives yours.

How do I know a product is a tested assembly?

Look at the label and the listing. The label shows the manufacturer, the certification agency, the rating and the test standard. For hardware, the SDI points to the UL and Intertek online listings as the way to verify that a selection may be used in a fire-rated assembly.

How long should I keep the approved documents?

The approved set must stay at the work site and be open to inspection while work is under way. After that, keep it with your inspection and maintenance records. Your local authority may set a longer retention rule.

Sources

Older Posts Newer Post