Yes, you can put an electric strike on a fire-rated door, but only if it is fail-secure and the strike, lock, frame and door are approved to work together. A fail-safe strike is the wrong choice on a fire door. Guidance from the National Institutes of Health says fail-secure strikes must be used on fire-rated doors per NFPA 80. This guide covers how a strike works on a rated opening, what the codes ask for, how to check compatibility, and what to confirm with your local authority before you buy.

Ufdoors
Keep Fire Door Hardware Compatible
Ufdoors manufactures and installs fire-rated steel doors, frames and hardware, helping contractors and property managers address NYC fire and safety standards.
Explore fire-rated door solutions

TL;DR

  • Use a fail-secure electric strike on a fire-rated door. The latch must stay held in the frame if power is lost.
  • The strike must be listed for use on fire-rated openings and must match the door, frame and lock it is installed with.
  • Egress rules still apply: the person inside must be able to leave freely, whatever the access control does on the outside.
  • Many jurisdictions require a permit and inspection for electrified locks on fire doors. Ask the authority having jurisdiction (AHJ) first.
  • Never cut the frame or the door in the field without checking the listing. Order the frame prepared for the strike.

Table of Contents

How an electric strike works on a fire door

An electric strike is an access control device that replaces the fixed strike plate in a door frame. A normal strike plate is a keeper. The latch bolt of the lock catches on it and holds the door shut. An electric strike does the same job, but it can release the keeper when it receives a signal from a reader, keypad or buzzer. The latch does not retract. The keeper moves out of its way, and the door opens.

Electric strike keeper beside a fire door latch

That design is why strikes suit fire doors better than many other electrified locks. A fire door has one main job: to close and stay latched so flame and smoke stay on one side. The latch is part of that job. With a strike, the mechanical latch of the lock stays in place. The door still closes on its closer, the latch still engages, and the strike holds the latch in the frame.

Two points follow from this:

  1. The strike is part of the fire-rated assembly. It is not an accessory added afterward.
  2. Whatever is done to the frame to fit the strike is a modification to a tested and labeled product.

A fire door assembly is made of a door, a frame, hinges, a latching lock, a closer and often a label on each part. Testing covers the assembly as built. Change a part and you may leave the tested range.

Fail-secure or fail-safe: the rule for fire doors

Electric strikes come in two power behaviors.

Type Without power On a fire door
Fail-secure Keeper stays locked. The door cannot be pushed or pulled open from the outside. Acceptable when listed for the rated opening
Fail-safe Keeper releases. The latch is no longer held. Not acceptable on a rated door

The reasoning is simple. During a fire, power may be cut or fail. If the strike releases without power, the door can swing open under heat and pressure, and the latch is no longer holding it. NFPA 80 therefore calls for fail-secure strikes on fire-rated doors. The NIH technical bulletin notes that fail-secure strikes are typical, and that there are only a few situations where access on a fire alarm is required.

Does fail-secure trap people inside?

No, as long as the lock is set up for free egress. Fail-secure refers to the outside of the door. The lock on the inside still lets people leave by turning a lever or pushing a bar, because the lock’s latch retracts mechanically. The strike only controls who can enter. This is the main reason a fail-secure strike works well with a mortise lock, cylindrical lock or exit device that has a lever or push-pad on the inside.

What about hold-open and fire alarm release?

Some buildings want a door to unlock when the alarm sounds, so occupants can enter a stairwell, for example. That is a code and design decision for your design team and AHJ. It is not a reason to choose a fail-safe strike on a rated door without approval. The usual route is a fail-secure strike plus a signal from the fire alarm system where the code requires it.

What the codes say about egress

Fire rating is one question. Egress is the other, and both apply to the same opening.

The 2021 International Building Code addresses electrically controlled locks on egress doors. For electric locking systems, Section 1010.2.11 requires the locking system to unlock automatically on loss of power to the locking mechanism. Section 1010.2.12 requires sensor-release systems to unlock when the building’s automatic sprinkler or fire detection system is activated, if one is provided.

Those sections can look like they clash with the fail-secure rule. They do not, once you separate the two sides of the door. The code is about the direction of exit. A fail-secure strike keeps the latch held, but the person leaving still operates the lock’s lever or exit device, and the door opens without a key, tool or special knowledge. The strike affects entry. It does not touch the exit path, and it must be installed so that it does not.

Controlled entry and free exit paths

The International Code Council’s own technical writing makes the same point: egress must be maintained according to code regardless of the access control used on the opening. UL Solutions adds that code-compliant locking arrangements need to be integrated with life safety systems such as fire alarms, so emergency egress is never compromised.

NFPA 101 also covers electrically locked egress doors, with release criteria that in some provisions include release on loss of power. The proposals for the 2015 edition set out those arrangements. Editions and local amendments differ, so confirm which edition your jurisdiction has adopted.

Codes vary by place

The IBC and NFPA documents are model codes. Cities and states adopt them with changes. A rule that passes in one county may need an extra permit in another. In New York City, fire and building rules are administered locally, so a design reviewed elsewhere does not carry over automatically. If you are working outside the US, the standards and approvals will differ again.

Listings: what “fire-rated strike” means

A strike is not fire-rated just because the product page says so. Look for the test standard and the listing.

UL 10C is the standard for positive-pressure fire tests of door assemblies. UL notes that it includes electric strikes, while UL 1034 covers burglary-resistant electric locking mechanisms, including electric strikes. A strike used on a rated door should be listed or labeled for fire-rated use. UL also offers testing and assessment of fire doors and fire door hardware to UL 10B and UL 10C.

Positive-pressure testing matters because in a real fire, pressure builds on the fire side of the door and pushes against the latch and the strike. A strike that holds in a bench test with no pressure may not do the job in a furnace.

Ratings are documented for other fire-resistant building elements the same way. If you want to see how ratings and joints are recorded in practice, this overview of fire-resistant panel listings shows how 1 to 3 hour assemblies are specified. A door assembly needs the same discipline: a rating on paper, tied to a labeled product.

How to check that a strike fits your assembly

Use this order. It prevents most failed inspections.

  1. Read the door and frame labels. Note the rating (for example, 90 minutes), the manufacturer and whether the label shows the frame is a fire-rated frame.
  2. Check the lock. Identify the lock or exit device and its function. Most strikes are made for specific lock types: cylindrical, mortise, or rim device.
  3. Check the strike’s listing. Its data sheet should say it is listed for fire-rated openings and for which ratings, door materials and frame types.
  4. Match the cutout. The frame must be prepared for the strike’s cutout. Hollow metal frames are commonly ordered with the prep done in the shop, which is cleaner than field cutting.
  5. Confirm the fail mode. It must be fail-secure for a rated opening.
  6. Confirm the power and wiring plan. Voltage, power supply, and the fire alarm connection if required.
  7. Ask the AHJ whether a permit, plans or a witnessed test is needed (see below).

If the strike manufacturer’s listing does not name your frame and lock combination, do not assume it is covered. Ask the manufacturer or a qualified fire door professional to confirm in writing.

Common mistakes

  • Choosing a fail-safe strike because the access control vendor defaults to it.
  • Cutting a frame on site to fit a strike that was never listed for that frame.
  • Leaving the door unable to latch because the strike is out of alignment. A fire door that does not latch is a failed fire door, strike or no strike.
  • Adding a strike and forgetting that the door still needs a working closer.
  • Treating the strike as a security fix for a door that is already out of tolerance.

Permits, inspections and the authority having jurisdiction

An electric strike on a fire door often counts as a special locking device. Some jurisdictions treat that as a permitted installation.

Fairfax County, Virginia gives a clear example. Its fire marshal’s requirements say a fire permit application, plan review and approval, and an issued permit are required before installing electrical or special locking devices on fire door assemblies. The same document says low-voltage inspectors must verify that a special-locks permit has been applied for before approving the low-voltage permit inspection.

That is one county’s process, not a national rule. Your jurisdiction may use different forms, names and fees. The point is the pattern: the electrical contractor, the door hardware supplier and the fire authority all have a role, and skipping a step can hold up a certificate of occupancy or a sign-off.

What to confirm before you order

Guidance for contractors says to coordinate with the appropriate AHJs and weigh applicable codes, life safety regulations, security requirements and the function of the facility before selecting access control hardware. In practice, bring these questions to the AHJ or a qualified fire door professional:

  • Which code edition and local amendments apply to this building?
  • Is a permit or plan submittal needed for the strike?
  • Must the strike connect to the fire alarm or sprinkler system?
  • Is a witnessed test or a post-installation inspection required?
  • Is this door part of an egress path, a stairwell, or an exit access corridor, and does that change the allowed hardware?
  • Who will keep the records: listings, labels, wiring diagrams and test results?

Our perspective

Most of the fire door problems we see start before the strike is chosen. They start with a frame that was never prepared for one. The access control plan is written after the doors are bought, and then someone has to cut a labeled frame in the field. That is slow, and it can leave the opening without the approval it needs.

Our advice is to settle the hardware plan first. Decide the lock function, the strike type and the fail mode, then order the door, frame and hardware as one set. We supply and install fire-rated steel doors, hollow metal frames and commercial door hardware, and we work to NYC fire and safety standards. That means we ask the same questions in this article on every job: what is the rating, what is the lock, who is the AHJ, and what does the listing say.

We also keep one rule simple. If the paperwork does not support the combination, we do not recommend it. A fire door that looks finished but cannot be signed off costs the owner more than waiting for the right part. For emergency replacements, we can often move quickly with same-day or next-day delivery, but speed never replaces the listing check.

— Esteban

Getting the door, frame and hardware as one set

If you are replacing a fire door or building out a new opening that will take an electric strike, start with the door unit. Our fire-rated steel door units combine a 90-minute door and frame, and our 90-minute fire-rated steel door unit with lock shows the set approach. For hardware, browse our fire-rated lever lockset and the rest of the range on Ufdoors, then tell us about your strike so the frame prep matches.

30 x 84 Knock-Down Steel Door Frame (Commercial Grade)

Contractors and property managers can also ask about bulk pricing, custom sizing, installation and emergency replacement. Prices are quoted per project, so contact us with the rating, quantity and opening details.

For a wider look at ratings and requirements, see our guide to fire-rated doors, ratings and how to choose.

FAQ

Can any electric strike be used on a fire-rated door?

No. It must be fail-secure and listed for fire-rated openings, and it must suit the lock and frame in your assembly. A strike sold for general access control is not automatically approved for a rated door. Check the data sheet and the listing before you order.

Why is a fail-safe strike not allowed on a fire door?

A fail-safe strike releases the keeper when power is lost. In a fire, that can leave the latch unsupported, and the door can open under pressure. Fire-rated doors need to stay latched, which is why fail-secure is the rule under NFPA 80.

Does a fail-secure strike block people from leaving?

No, not when the lock allows free egress from the inside. The strike controls entry from the outside. The lever, push bar or exit device on the inside still retracts the latch mechanically, so people can leave without a key or a power supply.

Do I need a permit to install an electric strike on a fire door?

Often, yes, though it depends on your jurisdiction. Fairfax County, for example, requires a permit and plan review for special locking devices on fire door assemblies. Ask your local fire or building authority before work begins.

Can I cut an existing fire-rated frame for a strike?

Only if the frame and strike listing allow it, and your AHJ accepts it. Field cutting can take the frame outside its tested range. A frame prepared for the strike before it ships is the safer route.